The Secretariat recommends the following three dates to be displayed in an EPD: 

  • "Publication date" (sometimes referred to as "issue date" or "registration date"). This date is set as the date when the company submit the EPD registration. In case the documentation is incomplete or contains errors, the publication date on the EPD should be updated to correspond to the date of the final resubmission for registration. This date remains the same even with later updates of the EPD. 
  • "Revision date". In case of a new version of an already-published EPD, this date should be set corresponding to the date when the updated EPD is submitted for publication. It should not be included in case of a first EPD edition.
  • "Validity date". This date is set during verification as normally +5 years (depending on rules in PCR) from the finalization of verification/date of the verification report.

Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select atleast one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article