How long does it take to develop a new PCR?

Created by Ariadna Serra, Modified on Tue, 12 Mar 2024 at 03:27 PM by Ariadna Serra

The full process usually takes 8-10 months. 


Normally from initiation to start of open consultation (i.e. the preparation of the first draft): 1-3 months. 

Open consultation 2 months. 

Update of the PCR based on the Open consultation: 1-2 months. 

Review: 6 weeks. 

Final update and publication 1-2 months.

Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select atleast one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article