How long does it take to develop a new PCR?

Created by Ariadna Serra, Modified on Mon, 30 Sep at 11:12 AM by Ariadna Serra

The full process usually takes 8-12 months. Normally from initiation to start of open consultation (i.e., the preparation of the first draft): 1-4 months. Open consultation 2 months. Update of the PCR based on the Open consultation: 1-4 months. Review: 2 months. Final update and publication 1-2 months.